Announced
CREȘTEM IMM – non-reimbursable financial support for developing a business
Organizația pentru Dezvoltarea Antreprenoriatului · The CREȘTEM IMM support instrumentVerified 13.11.2026 · rules v2 · official source ↗ (opens in a new tab)
Key points
- Submission deadline
- 20.11.2026
- Who can apply
- SMEs with economic activity in the Republic of Moldova for more than 24 months before submission
Conditions
Who can apply
- SMEs with economic activity in the Republic of Moldova for more than 24 months before submission, with financial statements (BNS) or unified tax returns (SFS) for at least the last two consecutive years and positive equity (with the exceptions provided), that invest in the digital transition, the green transition or technological modernisation and energy efficiency. Exception from the length of activity: beneficiaries that have successfully implemented the launch support under this Instrument (with post-funding monitoring) or with investments of more than 5 million lei. The activity of the investment must be listed in Annex 4. (points 14.1, 14.2, p. 19–20)
- Activity of more than 24 months before submission (point 14.1 (1), p. 19)
- Financial statements (BNS) or unified tax returns (SFS) for at least the last two consecutive years, with a positive/stable trend and positive equity (point 14.1 (2), p. 19)
- Negative equity in the last financial year → not eligible, except for a documented, demonstrated recovery (operating profit, positive EBITDA, cash, debt reduction); exception: the years with a state of emergency (Law no. 212/2004) (point 14.1 (3), p. 20)
- Exception from (1)–(3): beneficiaries that have successfully implemented the launch support under this Instrument (with post-funding monitoring) or that demonstrate investments of more than 5 million lei (point 14.1 (4), p. 20)
- Not part of a group of affiliated enterprises that together exceed the SME thresholds (point 14.1 (5), p. 20)
- The general eligibility criteria (1)–(17), cumulative: an SME under Law no. 179/2016; no non-SME member with a share of more than 25% (exception: non-commercial organisations); not an importer of goods subject to excise duties; not a fiduciary/insurance company, collective investment undertaking, bank, NBFI/SCA, pawnshop/exchange office, gambling, voluntary pension fund; no repeated violations found by state control; not in insolvency/reorganisation/liquidation/suspension (point 12, p. 16)
- The general eligibility criteria (continued): no arrears to the national public budget; no founders from non-transparent jurisdictions; no beneficial owners under restrictive measures; no conflict of interest with the management of IP ODA and no sanctions in the last 3 years for corruption/fraud/misuse of public funds; no other public support for the same investments (point 12, p. 16)
How much you can receive
| digital transition | green transition | technological modernisation and energy efficiency | |
|---|---|---|---|
| Micro-enterprise | 35% / 1.000.000 | 50% / 1.500.000 | 35% / 1.500.000 |
| Small enterprise | 30% / 1.500.000 | 45% / 2.000.000 | 30% / 2.000.000 |
| Medium-sized enterprise | 25% / 2.000.000 | 35% / 3.000.000 | 25% / 3.000.000 |
Amounts in MDL. Source: p. 10), share / ceiling per objective: Micro-enterprise – digital transition 35% / 1.000.000 MDL; green transition 50% / 1.500.000; technological modernisation and energy efficiency 35% / 1.500.000 (point 10 letter B, Table 2, p. 10
The text in the regulations
- Table 2Source: p. 10), share / ceiling per objective: Micro-enterprise – digital transition 35% / 1.000.000 MDL; green transition 50% / 1.500.000; technological modernisation and energy efficiency 35% / 1.500.000 (point 10 letter B, Table 2, p. 10
- Table 2: Small enterprise – digital transition 30% / 1.500.000 MDL; green transition 45% / 2.000.000; technological modernisation and energy efficiency 30% / 2.000.000 (point 10 letter B, Table 2, p. 10)
- Table 2: Medium-sized enterprise – digital transition 25% / 2.000.000 MDL; green transition 35% / 3.000.000; technological modernisation and energy efficiency 25% / 3.000.000 (point 10 letter B, Table 2, p. 10)
- SME founded by a woman or a young person: the share increases by 10 percentage points, only once if both are met (point 10 letter B, Specific conditions 1), p. 10)
- The support can be accessed for several objectives at the same time or in several stages, up to the maximum ceiling of each objective (point 10 letter B, Specific conditions 2), p. 10)
- Beneficiaries of previous programmes with the same objectives can take part only up to the maximum ceiling per objective, taking into account the funding received (point 10 letter B, Specific conditions 3), p. 10)
- De minimis aid: total de minimis aid over 3 years + the support granted ≤ 5.000.000 MDL (General conditions 1), p. 11; point 10.4 sub-point 12), p. 14); exception from qualifying as de minimis: funding for agriculture, forestry and fisheries (point 6, p. 8)
What is funded
- The activity in which the investment is made must be listed in Annex 4 (per objective), not necessarily the core activity (point 14.2, p. 20; Annex 4, p. 29–30)
- The plan is aligned with one or more objectives in Table 2; the applicant allocates the items to objectives in the Form; IP ODA may adjust it, with the applicant's agreement (point 10.1 sub-points 5)–6), p. 12)
- Renewable energy: only for own consumption (the invoices for the last 12 months); a surplus of up to 20% above the demonstrated consumption; «If a feasibility study is presented, the 20% surplus does not apply»; capacity above the limit is borne by the applicant; no sale of energy to the grid (point 14.3 letter C, p. 23)
- Purchases are eligible only if made after the plan is submitted; earlier advances are eligible only if, cumulatively, ≤ 50% of the value of each item and made no more than 6 months before submission (point 13.3, p. 18; point 14.3, p. 20)
- Digital transition: specialised ICT hardware, servers/storage/networking, dedicated components (GPU etc.), including installation and commissioning (point 14.3 letter A sub-point 1), p. 20)
- Digital transition: software applications/licences, databases; ERP/CRM systems; digitisation of archives; artificial intelligence solutions (point 14.3 letter A sub-points 2)–5), p. 20)
- Digital transition: IT services for e-commerce – each activity a)–e) ≤ 10% of the priority's maximum grant (point 14.3 letter A sub-point 6), p. 21)
- Digital transition: Cloud and SaaS services; cybersecurity; consulting for the technical documentation (≤ 10% of the priority's maximum grant); staff training; cash reduction technologies (point 14.3 letter A sub-points 7)–11), p. 21)
- Digital transition: subscriptions (CRM, ERP, SaaS, Cloud, domain, hosting, AI) – funded for a maximum of 24 months from contracting (point 14.3 letter A, p. 21)
- Green transition: equipment for pollution prevention and waste management (point 14.3 letter B sub-point 1), p. 21)
- Green transition: equipment for water resource management (point 14.3 letter B sub-point 2), p. 21)
- Green transition: equipment for reducing air pollution (point 14.3 letter B sub-point 3), p. 21–22)
- Green transition: equipment for preventing soil pollution (point 14.3 letter B sub-point 4), p. 22)
- Green transition: consulting for sustainable production and consumption, environmental management, green certifications, ESG, equipment required by the standards (point 14.3 letter B sub-point 5), p. 22)
- Technological modernisation: modern equipment, machinery and technological lines, industrial robots, modernisation of existing lines (point 14.3 letter C sub-points 1)–3), p. 22)
- Technological modernisation: protected-field agricultural production systems, only for horticultural production (point 14.3 letter C sub-point 4), p. 22)
- Technological modernisation: logistics technologies and solutions for added value / the value chain (point 14.3 letter C sub-point 5), p. 22)
- Energy efficiency: solar water heating systems; production and/or storage of renewable energy; biogas; heat pumps, biomass plants (point 14.3 letter C sub-points 6)–9), p. 23)
- Consulting for the business plan: up to 2% / 4% / 6% of the approved grant; consulting for issuing bonds or listing on the stock exchange ≤ 300,000 lei (point 14.3 letter D, p. 23)
What is not funded
- Green transition: equipment intended for household or administrative use that does not contribute directly to the enterprise's technological process is not eligible (p. 21), nor are heating/air-conditioning systems for the general comfort of administrative or social premises (p. 22) (point 14.3 letter B)
- Self-propelled agricultural machinery: not eligible for development, except for activities that cannot be funded from FNDAMR (point 15 «17)», p. 24)
- Ineligible expenses: a) taxes and duties; b) foreign exchange losses; c) leasing or loan costs; d) rent/lease of premises, offices, land; e) consumables and administrative expenses; f) purchase/construction of residential or administrative buildings; g) second-hand equipment/machinery (point 15, p. 24)
How it is evaluated
- Refusal if the investments actually fall under an objective whose call is closed (point 10.4 sub-point 15), p. 14)
- Application through a call, on a counter basis, within the budget, according to the calendar announced on the IP ODA website (point 10.1 sub-point 3), p. 12); exhausting the budget of an objective suspends submission for that objective (point 7, p. 9; point 10.1 sub-point 7), p. 12)
- If more than 30% of the mandatory and additional documents are missing (including the tables on the financial situation and forecasts) → the file is returned for non-compliance and does not affect the counter (point 10.1 sub-point 4), p. 12); the same lack is also a reason for refusal (point 10.4 sub-point 3), p. 14)
- Pre-funding assessment: compliance, economic and financial, business plan, risks; high/medium/minimum risk level; additional documents may be requested (payment orders for advances, the lender's confirmation for the own contribution, accounting breakdowns, contracts/pre-contracts etc.) (point 10.2 sub-points 2)–7), p. 12–13)
- Minimum score of 50 on the evaluation grid (Annex 5 / Annex 6) (point 10.2 sub-point 8), p. 13); the final decision belongs to the IP ODA Funding and Risk Committee (point 10.3 sub-point 1), p. 13); «Projects will be approved in descending order, according to the score obtained, within the budget available for the call. Where the files of the applicants for support under the Instrument have obtained the same score, the ‘first come, first served’ principle will apply.» (point 10.3 sub-point 3), p. 13)
- The Committee may impose conditions, e.g. the average gross salary ≥ 70% of the average salary in the sector, capitalisation of the net profit (point 10.3 sub-point 4), p. 13)
- The reasons for refusal 1)–16) (point 10.4, p. 14)
- If the applicant is a beneficiary of this Instrument or of other IP ODA instruments, or applies with several business plans at the same time, the pre-funding assessment takes into account their degree of implementation and the applicant's financial capacity; «A new business plan may be approved only after the investment related to the ongoing projects has been fully completed.» (point 10.3 sub-point 5), p. 13)
Instalments and payments
- Instalments: 50% after the contract is signed; 50% after proof that the own contribution has been invested and the investment from the first instalment has been made (point 11.1 sub-point 7) letter B, p. 15)
After approval
- Funding contract + surety contract (usually with the partners/shareholders) (point 11.1 sub-points 1) and 4), p. 14–15)
- The maximum implementation period: 9 months, extension only on a reasoned written request (point 11.1 sub-point 6), p. 15)
- Monitoring for 24 months after the plan is completed; a progress report every 6 months (point 11.2 sub-points 2) and 4), p. 15–16)
Required documents
- The application form (the business plan), submitted online, according to the template set by IP ODA, signed with a qualified electronic signature by the applicant or the legal representative (point 10.1 sub-point 1), p. 11)
- Financial data on the main existing and planned financial and economic indicators – mandatory (point 10.1, Table 3 no. 1, p. 11)
- Price quotes containing the technical specifications of the goods/services requested – mandatory (point 10.1, Table 3 no. 2, p. 11)
- The Provider/Supplier selection sheet – mandatory (point 10.1, Table 3 no. 3, p. 11)
- Existing licences and permits issued in the enterprise's name – if the activity requires them (point 10.1, Table 3 no. 4, p. 11)
- A valid power of attorney – if the applicant is represented by another person (point 10.1, Table 3 no. 5, p. 11)
- The entrepreneurship training certificate (IP ODA start-up programmes) and/or entrepreneurial knowledge (experience, graduation certificates, diplomas) – only if the plan is submitted on behalf of a newly registered enterprise (point 10.1, Table 3 no. 6, p. 11)
- Documents confirming the right to use the production premises (ownership; lease/loan for use) – for applicants with production activity (point 10.1, Table 3 no. 7, p. 11)
- Execution project – for investments in systems and installations for producing, storing or using energy from renewable sources, heating systems and other technological installations which, under the legislation, require an execution project (point 10.1, Table 3 no. 8.1, p. 11)
- Grid connection approval, the consumption invoices for the last 12 consecutive months or a feasibility study – for investments in systems producing and/or storing electricity connected to the grid; the approval is not needed for fully independent systems (point 10.1, Table 3 no. 8.2 and Note, p. 11–12)
- Terms of reference – for a business plan that involves developing complex software applications (point 10.1, Table 3 no. 9, p. 12)
- The declaration on the de minimis aid received in the last 3 years, including the current year – an obligation of the beneficiaries; it is not listed in Table 3, the time of submission is not specified in v5.0 (point 6, p. 8)
Reference to the source: ODA, the CREȘTEM IMM Instrument v5.0 (Minutes no. 20 of 28.10.2026), points 6, 10 letter B (Table 2), 10.1–10.4, 11.1, 12, 14, 15; Annexes 4 and 6
- Funder
- Organizația pentru Dezvoltarea Antreprenoriatului
- Programme
- The CREȘTEM IMM support instrument
- Opening
- 16.11.2026
- Rules version
- v2 · approved by the ARFIO team on 13.11.2026
Important
The check does not mean approval. The decision belongs to the funder. The data on the sheet is updated with every version of the regulations.
Version history
- v2 · 13.11.2026 · current · Instrumentul CREȘTEM IMM v5.0 (PV nr. 20 din 28.10.2026): selecția după punctaj, regula nouă de la pct. 10.3 subpct. 5), trimiterile de pagină; fereastra 16–20.11.2026 (rules-verifier, 2026-11-13)
- v1 · 28.10.2026 · superseded · CREȘTEM IMM v4.0 (verificat de rules-verifier la 19.10.2026); fereastra din noiembrie după calendarul ODA, 2026-10-28